Dear expert,

Contractor have been qualified 02 WPS  for SMAW process and FCAW process independent welding process. The FCAW process is using the for the CJP  of structure part with only FCAW process and then they brought the SMAW process to Weld on the FCAW process Which have been welded, is this possible to use FCAW process and then SMAW process Without qualifying to combine 02 welding process together.

Code apply: AWS D1.1.

Please advise

 

Best Regards,

 

Thuan

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...