Dear Experts,

In a cross-country pipeline project I found crack in the RT film. The length of the crack is about 100mm. My colleagues (QC) told me to CUT-OUT the joint. Is it mandatory to cut-out a weld after finding crack regardless the length of the crack as per API 1104? I do not find the term cut-out in any type of codes and standards. Is re-weld means cut-out? In my project applicable standard is API 1104.

Regards,

MD SAIDUR RAHMAN


--
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CACqsNK%2BocRe3yHg2dvyPWVZSAxQfPjpKkM%3DOSqEOBfJ6QhxsmQ%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone