Dear Chandra,
If the piping class and weld joint required PWHT ,Same line support pad(directly weld to the pressure part pipe)only required PWHT.
Regards,
PETER SOLOMAN
On Sat, Mar 24, 2018 at 4:42 PM, Vairamuthu <vaira.muthu.78@gmail.com> wrote:
Yes. PWHT required as it is directly welded to pressure part.
On Thursday, December 21, 2017 at 9:14:19 AM UTC+3, bapun wrote:Dear ExpertKindly help me out to decide whether we have to perform PWHT or not for Pipe to Saddle support fillet welding .Design Code ASME B 31.1 .The details given below and its a long distance pipe rack jobThe saddle material is ASTM A387 GR 11.The welding type is fillet welding.HP pipe detail - DN-350,THK-28 mm and Material ASTM A 335 P11.--tHanks & rEgardsChandra Bhanu Mohapatra--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com .
Visit this group at https://groups.google.com/group/materials-welding .
For more options, visit https://groups.google.com/d/optout .
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment