Dear Experts,
Yesterday our client reject to exchanger hydro test.
Normally we use two gauge. Actually one gauge for equipment vent high point. One gauge for equipment connected manifold itself low point.
But client requirement equipment Drain itself.
That the reason he rejected hydro.
Can anybody explain gauge for equipment connected manifold itself it is accepteble or not?
Any code reference / clear Detail .
Thank you.