Friday, March 9, 2018

[MW:27479] Exchanger hydro test

Dear Experts,

Yesterday our client reject to exchanger hydro test.

Normally we use two gauge. Actually one gauge for equipment vent high point. One gauge for equipment connected manifold itself low point.

But client requirement equipment Drain itself.

That the reason he rejected hydro.

Can anybody explain gauge for equipment connected manifold itself it is accepteble or not?

Any code reference / clear Detail .

 

Thank you.

KM.


--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...