RE: [MW:27486] Exchanger hydro test

To accept any hydro test its necessary to disconnect any source of energy.

It's necessary to disconnect the manifold.

 

 

 

Hernán Castillo Mier

Profesional Especialista de Equipo Estático

FACILITADOR AUTORIDAD TÉCNICA EQUIPO ESTÁTICO

INSPECTOR AUTORIZADO

API 510 (33119)

Avantel: 8*1571

Teléfono: 668-2396

 

De: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] En nombre de PK M
Enviado el: viernes, 9 de marzo de 2018 12:01 AM
Para: materials-welding@googlegroups.com
Asunto: [MW:27479] Exchanger hydro test

 

Dear Experts,

Yesterday our client reject to exchanger hydro test.

Normally we use two gauge. Actually one gauge for equipment vent high point. One gauge for equipment connected manifold itself low point.

But client requirement equipment Drain itself.

That the reason he rejected hydro.

Can anybody explain gauge for equipment connected manifold itself it is accepteble or not?

Any code reference / clear Detail .

 

Thank you.

KM.

 

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:34874] ASME IX, groove weld during WQT limits for Fillet Weld production

Hi David,  There are two points in WQT. 1. Thickness of Base Metal -T 2. Thickness of Weld Metal -t When you use a combination of two proces...