Dear
Suppose, project spec specifies any additional tests during PQR, then you have to go for new PQR incorporating all project specific variables / requirements.
B31.1 OR B31.3 does not deal with any welding qualification requirements.
Regards
R Vairamuthu
On Saturday, March 24, 2018 at 7:37:06 PM UTC+3, Maghroud Moussa wrote:
Dear experts.
I have a PQR for P1 (GTAW, PWHT)qualified with Sec IX and B31.3. Is this PQR can used to supporte PQR in a power plant project that the code is B31.1.