Friday, November 25, 2011

Re: [MW:13056] PIPE TO PIPE BRANCHING

Hi Harsha,

If you will go for stub in , then you have to provide a reinforcement pad.welding will be more in that. If it is high pressure line, you should better go for stub in where you can go for full penetration joint and no need of reinforcement pad.


From: harsha bhat <harshnb@gmail.com>
To: materials-welding@googlegroups.com
Sent: Thursday, November 24, 2011 11:16 PM
Subject: [MW:13049] PIPE TO PIPE BRANCHING

Dear Experts,


Can anyone please tell me in case of pipe to pipe branching is it stub-in or stub-on, which one would be the preferred choice.

On the out set it seems that stub-in would be preferred if the line is of higher rating. But still will be helpful if anyone would give their opinion on the same.

Thanks in advance,
Regards,
Harsha Bhat.


--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.


No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...