Dear Experts, When we are using two process (GTAW + SMAW) on pipe test coupon of a PQR, Root run & hot is done with GTAW process, immediately after hot pass we have started SMAW process, Prior to start of SMAW process, temperature of coupon noted was 95 deg C My question is whether this 95deg C will be considered as preheating temperature for SMAW process Kindly advise in the light ASME Codes Thanks in advance Mhaskar Aly UAE | ||
|
Tuesday, November 29, 2011
[MW:13083] Preheating temperature of 2nd process when use two welding process in one single joint (GTAW+SMAW)
Subscribe to:
Post Comments (Atom)
[MW:35346] Cast-iron welding
Any advice for cast iron welding Sent from Yahoo Mail for iPhone
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-
Section I. PRINT READING 3-1. GENERAL a. Drawings . Drawing or sketching is a universal language used to convey all necessary information to...
No comments:
Post a Comment