Dear
Of course it is not acceptable and as such the client has right to raise NCR.
Now you can close the NCR as per your Management system procedure.
Thanks
On Tue, Jul 24, 2018, 5:17 PM SRINI <kanna.qc@gmail.com> wrote:
Dear All--My client raised NCR for founding leakage during water fill on GRE pipe at run pipe. Leak found During time of water filling and before starting hydro test.Could any body please explain me raised NCR is acceptable or not.AS per ITP- 6.3 is water filling stage6.4 is hydro test.Please reply me in urgent basis.RegardsSrinivasan.A
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment