incomplete fusion is a major in GMAW with solid wire not with FCAW
kgp
On Wed, Apr 21, 2010 at 11:12 PM, sachin sankhe <sachin.sankhe@rediffmail.com> wrote:
Hi,
We`have FCAW welding for pressure part in refinery service
As FCAW welding mainly have discontinuities like incomplete fusion
So we have specified 100 % RT/MP/DP
However UT is more preferred over RT for planar defect due to incomplete fusion
I feel 100 % RT to be replaced by 100% UT
Request you to give your opinion
Regards
Sachin.Sankhe
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment