Re: [MW:22000] tube to tube sheet qualification.

Thanks hegde sir for valuable revert,
Still have little bit query,
I have two separate qualifications of mock up for same pattern, but only thing is one is with addition of filler wire, another one is without addition of filler,
But in actual job, now welder is welded intially by fussing ( 90 % of welding without addition of filler) then unfilled portions are welded by adding filler wire to achieve good finish.

So shall I make single mock up wps using those two pqrs,
If no, then Wat to do in above case,
If I need to again qualify mock up procedure in single pqr using initially wihout filler and then by addtion of filler wire ,is it allowed by code?

Regards
Mahesh mirje

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm

The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...