Friday, September 19, 2014

[MW:21931] Tube to tubesheet pull out test load calculation


Dear Experts,

Please explain following
1) How to calculate Tube to tubesheet pull out test load as per ASME Sec VIII Div.I Nonmandatory appendix A. Pls. provide pullout test load calculation of tube to tube sheet weld with different joint design
2) What is difference between fr (Test) & fr (No Test) & how to select Joint Type as per Table A-2
3) Efficiency Value given in Table A-2 is minimum or maximum


Thanks & Regards
Yogesh P.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone