I don't believe there is any requirements, but on P5-B materials, it is a common practice as cracks have been known to form after 24 hours on these materials. I have heard of some materials on "Hold" pending another RT after the initial test after 7 Days.
I have just completed PWHT on ASME 1 piping and there is no requirement on P1 material for additional RT after cool down.
----- Original Message -----From: Luis AlbanesSent: Thursday, May 20, 2010 6:30 AMSubject: [MW:5198] NDT after PWHT
Dear friendsWe just finished PWHT in an LPG sphere acording to ASME VIII section I, and I can´t find in the code the part that obligues to Xray after this treatment, any one has experience with this? where does ASME VIII say it has to be done?Thank youLuis Albanés
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment