[MW:5215] A860WPHY

Dear Members,
We are to weld the A860 WPHY 65 Flow Tee to A333 Gr6 pipe.Our TPIA is asking for a separate PQR for this.We already have a PQR fpr A333 Gr6. Our main concern is if        we onduct a PQR fpr A860WPHY TO A333Gr6 we will loose one Flow Tee which we have imported from ITALY.To get a new Floe tee it will take minimum three months which we can not afford at this point of time. Is there any way out.
 
 