Tuesday, October 26, 2010

Re: [MW:7835] Deletion of filler metal in WPS ASME IX

Case1 pqr is not suitable for case2 , addition or deletion of filler is essential variable.


 
2010/10/26 César Alexis Viteri Pérez <alexis_viteri@hotmail.com>
 

Dear members,

 

CASE 1:  GTAW , WT QUALIFIED 1/8" – 5/16", WITH FILLER METAL, groove V joint

CASE 2: GTAW, WT 1/16" , NO FILLER METAL , buttweld

 

Could you please give your opinión regarding this issue:

There is a PQR approved by ASME IX for case 1, is suitable use that PQR for support a new  WPS in order to weld as described in case 2?

 

Thanks and regards

AV

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...