Wednesday, October 27, 2010

Re: [MW:7869] WQT- Number of Welders Issue

Limesh
 
I understand that, it has not been allowed to weld by 2 welders on single pipe as pr ASME latest revision.
 
I don't have latest edition, but you can find recent article in Welding Journal (Aug 2010) discuss about this issue.
 
Regards
 
K.Babu
Singapore
 
----- Original Message -----
From: limesh M
Sent: Wednesday, October 27, 2010 6:12 PM
Subject: [MW:7868] WQT- Number of Welders Issue

Dear All,

Design Code – ASME B31.3

Welding Code – ASME BPV SEC IX

Can I use multiple welders in a single test coupon for WQT.ie, two welders one half with two process (6 o'clock to 12 o'clock) and other half (6 o'clock to 12 o'clock) another two welder with two process(Suppose all welders are crossing the minimum 6"(150 mm) length)?

Is there any clause insisting that one welder has to weld the entire pipe circumference irrespective of diameter?
 
Regards,
 
Limesh

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34916] Applicability of Impact requirement as per ASME B31.3

Dear All, Design code – ASME B31.3, Welding Code- ASME BPVC SEC IX Material  to be used used during Fabrication - SA 333Gr6 (P No.1 G...