Dear experts,
Kindly solve my query.
My requirement for the Steam/Boiler drum : Intermediate SR (PBHT) followed by shell rolling & final SR(PWHT) followed by aftyer completion of drum welding.
i qualified WPS as per ASME sec IX & EN ISO 15614-1 only with Final PWHT.
Material:SA516 gGR 70/WB36
But for my job having intermediate SR also. Is it requred to qualify WPS with PWHT followed by intermediate SR (PBHT)? If required to qualify, based on which
clauss we have to follow?and where we have to mention in the WPS?
--
THANKS & REGARDS
KALYAN VVV
WELDING ENGINEER
HYDERABAD
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment