Dear Mr.Dajidalam Mohd.

As far as my knowledge &  as  worked in Verious American  Projects for shop floor line pipe inspection for Dove Chemicals and verious other projects, as per APL line pipe Repair in pipe is accepted in certain depth of welding from out side only (i.e.ID repair is not permited). Suggested for Cut-off  due to Burn through problem.(i.e.Repair is not permitted for Burn through).Pl be analises API 5L properly .At present API 5L Code book not available with me however I shall come back to you shortly.
If anythings else pl revert mail.

Regards,

RK Vichare
Mumbai-India.

----- Original Message -----

From: sajidalam mohd.

To: materials-welding@googlegroups.com

Sent: Sun, 18 Sep 2011 16:58:32 +0530 (IST)

Subject: [MW:12477] WELD DEFECT:-BURN THROUGH IN SAW WELDING IS ACCEPTABLE FOR PSL2 PIPES



DEAR ALL


             NOTHING IS MENTIONED ABOUT WELD DEFECTS BURN THROUGH IN API 5L 44TH ADDITION FOR PSL2 PIPES.


 


I WANT TO NO IF BURN THROUGH DEFECTS COME BY SAW WELDING IT IS ACCEPTABLE OR REJECTABLE FOR PSL2 PIPES.


 


REGARDS


MOHAMMAD SAJID ALAM


INSPECTION ENGINEER


AICO-DAMMAM


MOBILE:-0534077860








--


To post to this group, send email to materials-welding@googlegroups.com


To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com


For more options, visit this group's bolg at http://materials-welding.blogspot.com/


The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...