Hi venkateswaran
1) PWHT as per UCS-56 is mandatory for welded joints over 38 mm nominal thickness.
2) for welded joints of nominal thickness over 32 mm through 38 mm, PWHT is not required if preheat is applied at a
minimum temperature of 95 degree celcius during welding.
Please go through all the notes, in UCS-56 for exceptions.
Thanks
Murugesan
On Sat, Jun 25, 2011 at 3:14 PM, Venkateswaran <k.venkateswaran@ionexchange.co.in> wrote:
--Dear AllAs per ASME Sec 8,what will be the minimun thickness requirement to carryout PWHT for CS .Kl.refer me the page no/Table.Regards,K.Venkateswaran.
Please consider the environment before printing this E-mail
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment