You can clear the joint with ultrasonic inspection without
cutting and rewelding.
On 6/24/11, Shashank Vagal <nach_sam@yahoo.com> wrote:
> Dear members,
> By some oversight, MPI of one pipeline welds was not done on cut bevels. The
> PL section is now ready for hydrotest. Construction Code is API 1104 1999
> Ed.
> RT is acceptable. But this lapse is punchlisted. How do you resolve the
> issue?
> Cutting and rewelding is not permitted.
> Best regards,
> Shashank Vagal
>
> --
> To post to this group, send email to materials-welding@googlegroups.com
> To unsubscribe from this group, send email to
> materials-welding+unsubscribe@googlegroups.com
> For more options, visit this group's bolg at
> http://materials-welding.blogspot.com/
> The views expressed/exchnaged in this group are members personel views and
> meant for educational purposes only, Users must take their own decisions
> w.r.t. applicable code/standard/contract documents.
>
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment