Hi! Generally to avoid more PQR qualification ,, while qualifying PQR of P1 Gr1 and P1 Gr2 instead of qualifying TWO separate PQR It is better to Qualify PQR onone testcoupon having one of the plates of P1 Gr1 and other plate of P1 Gr2 and for Impact test, test Weld , HAZ of both side i.e. P1Gr2 , and P1 Gr1 With these testing the PQR is qualified for a)P1 Gr1 to itself b) P1 Gr 2 to it self Satisfying all essential and supplimentary esentials Regards Hegde P.B. --- On Fri, 22/6/12, samshuddin k <sam.renja@gmail.com> wrote:
|