Dear expert,
If welding procedure is qualified for the SA 516 Gr.60 to same (P No.1 Group 1 to same), then is it required to conduct another PQR for the SA 516 Gr.70 to same (P No.1 Group 2 to same), if impact requirement is applicable for both material at same temperature?
--
Regards
Lalit Vadadoriya
Sr.Engineer (Inspection)
Engineers India Limited
Dahej Petrochemical Complex,
Lalit Vadadoriya
Sr.Engineer (Inspection)
Engineers India Limited
Dahej Petrochemical Complex,
Dahej (Gujarat)
--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.