Dear experts,
P1 Material Pipe welding Joints RT and MT examination before PWHT is Acceptable or not ?
As per 2010 ASME B.31.3 para 341.3 Examination requirements,
(a) for P.nos 3,4 and 5 materials Examination shall be performed after completion of any heat treatment.
Thank you
YEM.