RE: CLARIFICATION FOR FIRST WELDE RADIOGRAPHY FOR WELDER( ASME SEC IX)

Thanks for your quick answer.

 

From: Raghuram Bathula [mailto:raghurambathula@gmail.com]
Sent: Monday, July 25, 2022 11:22 AM
To: Sam Raja.A; Materials-Welding
Subject: Re: CLARIFICATION FOR FIRST WELDE RADIOGRAPHY FOR WELDER( ASME SEC IX)

 

it is alternative as per ASME, however need to perform in addition to qualification if DEP is applicable in your project

 

On Sun, 24 Jul 2022 at 14:21, Sam Raja.A <samraja.a@gulfspic.com> wrote:

Dear Sir,

 

Is  first production required for already qualified welder/welding operator  as per sec ix qw-304.1/qw305.1?

 

It is mentioned shell dep specification.

 

Kindly advise us any code reference.

 

Thanks & Regards,

Sam Raja

QC Inspector,

Gulf Spic

Kuwait

Mob-+965-65007906

 