hi expert 
could anyone help es 
we need the code and standard used for  acceptance criteria and formulas of hydro test for undergound pipeline 
I cheeked API-1110 and i did not find any formulas, thanks for help expert

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/2e2f6f27-4000-4dab-a527-1cc628dafb84n%40googlegroups.com.

No comments:

Re: [MW:35354] Cast-iron welding