[MW:888] %RT on nozzle long seam per API650

Ref: API650 2007 edition

 

Para 5.7.8.11 states ‘All longitudinal butt-welds in the nozzle neck etc…………..shall receive 100% radiographic examination (see 8.1)

Where as in para 8.1.1 states ‘Radiographic inspection is not required for the following:…………welds in nozzle and man way necks made from plate’

 

Which one is correct or am I not interpreting correctly?

 

Note: if you are referring old editions it is same (just refer para 3.7.8.11 and 6.1.1 instead of the above)


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone