Hello, Can I know which dia electrode was used at 6 O'CLOCK & 12 O'CLOCK position. Regards Ramu
--- On Wed, 9/7/08, sachin sankhe <sachin.sankhe@rediffmail.com> wrote:
From: sachin sankhe <sachin.sankhe@rediffmail.com> Subject: [MW:907] Re: Hardness variation on a temper bead welded F65 forging To: materials-welding@googlegroups.com Date: Wednesday, 9 July, 2008, 4:20 PM
Hi, Actually as stated by me early we have first carried qualification in 5F position & later on 2F position. I had mentioned 6 O'CLOCK & 12 O'CLOCK position for 5F position
Thanks for explaining the reason.
Regards Sachin.Sankhe
On Tue, 08 Jul 2008 Bathula Raghuram(Mumbai - PIPING) wrote : >It is some thing tricky, and difficult to evaluate the exact cause. Your >assumptions regarding HI could be the reason for this at a particular >position. > >But one thing is not clear to me, you welded this piece in rotating, how >do you identify the 12'o clock position, where hardness is more? > >Yes your conclusions stated below will help us definitely in due course. > > > >Regarding your query on the previous statement the right vertical line >is toe of the weld and left vertical line is toe of the surface temper >reinforcing bead, this is mentioned to give a rough idea of surface >temper bead placement, please note these surface temper beads may remain >in place or may removed by grinding. > > > > The in tempered HAZ as shown with arrow. Attachment in the previous >post shows the same for tempering this arrow marked portion. > > > >________________________________ > > From: sachin sankhe [mailto:sachin.sankhe@rediffmail.com] >Sent: Monday, July 07, 2008 6:59 PM >To: materials-welding@googlegroups.com >Cc: Bathula Raghuram (Mumbai - PIPING) >Subject: Re: [MW:904] Hardness variation on a temper bead welded F65 >forging > > > > >Dear Mr.Raghuram/Members, > >Let me apologise for not putting subject. > >Yes I had taken care as mentioned in your mail >As u can see in attached figure that 8th pass was done on 6th pass. >Distance between welding edge of 6th pass & 8th pass(i.e vertical >distance in your mail sketch) was 3mm >Yes preheating was done min. 150 deg.C & INTERPASS temp maintained at >180-190 Deg.C > >Also why it give high hardness on 12 O'CLOCK POSITION ONLY whereas it >was accaptale in 6 O'CLOCK position > >Today I could see Macro of all specimen from DNV,Lab(Singapore).I >compared weld profile of both 6'O CLOCK & 12 O'CLOCK specimen.I have >noticed that fusion line in 12 O'CLOCK was not straight i.e When fusion >line deviated far into base metal at that point hardness value was too >high.So I think welder shall try to maintain fusion line straight. >Note that 2F position hardenss was OK > >So Conclusion is >If hardness is critical to achieve > >1.Weld in such aposition that more Heat I/P can be done.In this case >preferable position was 2F compare to 5F >2.During capping avoid welding on base metal >3.Grind 1/4th or may be 1/2 of last fill passes before doing capping so >that we can get good tempering of last fill pass >4.Last Capping pass(Temper bead technique) shall be not that close to >base metal so that it makes its own untempered HAZ in base metal > >Views on above concluded points are welcome > >I was not clear on your below statement can u be bit more clear on this > >"The distance between two vertical lines (as shown in attached sketch) >shall be small enough that HAZ of reinforcing bead tempers all of the >unaffected HAZ in the base metal, but not so small that it creates its >own untempered region." > >Regards >Sachin.Sankhe > > > > >On Mon, 07 Jul 2008 Bathula Raghuram(Mumbai - PIPING) wrote : > >Dear members > > > >Request to use appropriate subject line, thou the topic was very > >interesting to discuss, it may be ignored by many in absence of an > >appropriate subject line. > > > > > > > >There are chances that toe of the weld, where no tempering of HAZ has > >occurred, in addition there is weld metal that is also not tempered, it > >may be necessary to add a layer on top of the completed weld and grind > >it off to get the desired results. This results in tempering of the > >remaining untempered weld and HAZ. But be careful not to let this extra > >tempering layer penetrates to base metal, if it, then you may create a > >new untempered HAZ. > > > >The distance between two vertical lines (as shown in attached sketch) > >shall be small enough that HAZ of reinforcing bead tempers all of the > >unaffected HAZ in the base metal, but not so small that it creates its > >own untempered region. > > > >(Remember) Cooling rate during welding : Thicker one cool faster than > >thinner ones, with lower heat input cool rapidly than higher heat >input, > >cooler base material cool quicker than hotter ones (did you preheat >this > >one?) > > > > > > > > > > > >Invite more discussions, and active participation, irrespective of your > >views whether right or wrong as only in discussion we can improve > > > >________________________________ > > > > From: materials-welding@googlegroups.com > >[mailto:materials-welding@googlegroups.com] On Behalf Of sachin sankhe > >Sent: Saturday, July 05, 2008 6:52 PM > >To: materials-welding@googlegroups.com > >Subject: > > > >Dear Friends, > > > >Recently we have come across welding situation as mentioned below > > > >Details are as follows- > > > >1.Material used -API 5L X65 TO A694 F65 > >2.Position-5F > >3.Welding Process-GTAW(Root,Hot)/SMAW(Fill, Cap) > >4.Welding consumable-GTAW(ESAB OK 13.09),SMAW(E8016 GH4R) > >5.Welding Technique-Temper Bead Technique > >6Reference Codes-API1104/NACE MR0175/DNV 0S F101 > >7.Hardness Requiremnt as per Client Spec-248 HV10 > >8.Size(12" O.D X 27.3 mm Thk to 2" O.D X 8.7 mm Thk) > > > >Situation- > >1.We carried out welding procedure qualification and sent for testing > >2.Testing to be carried out-NICK BREAK & HARDNESS > >3.Hardness on capping pass (12 O'CLOCK )at forging side found above >250 > >HV10 > >4.However at 6 O'CLOCK it was below 248HV10 & hence acceptable > >5.Due to failure at 12 O'CLOCK POSITION,we decided to re-qualify. > >6.This time we maintained high heat input(1.6-2.0 kJ/MM) on caping pass > >at forging side > >7.Hardness result again we found high at same location as > >previous,however on 6 O'CLOCK position it was less then 248 HV10 > >8.Due to failure we decided along with client following option > > a)Two procedure to be qualified one in 5F position like prevoiusly >but > >this time we decided to rotate the pipe when welding capping pass on > >forging side i.e Welding to be carried out only b/w 9-6-3 o'CLOCK > >POSITION only.Thus avoiding welding in 12 O'CLOCK POSITION > >Also we decided to use even higher heat i/p by using larger dia. > >electrode (3.2 mm)in place of previoiuly used 2.5 mm electrode > > b)Secound procedure we decided to do in 2F position and maintaining > >higher heat i/p(1.8-2.5 kj/mm)on capping pass(Forging side) > > > >9.After hardness testing for 5F position results on 12 O'CLOCK position > >forging side again failed > >10.However in 2F position it was satisfactory with same heat i/p as >that > >in 5F position > > > >Would like to know the reason of such behaviour > > > >Sachin.Sankhe > >Engineer-Inspection > >Aker Kvaerner-Malaysia > >Mobile:012-2896901 > >Email1:Sachin.Sankhe@akerkvaerner.com > >Email2:Sachin.sankhe@rediffmail.com > > > > > > > > > >>
Sachin.Sankhe Engineer-Inspection Aker Kvaerner-Malaysia Mobile:012-2896901 Email1:Sachin.Sankhe@akerkvaerner.com Email2:Sachin.sankhe@rediffmail.com | Bring your gang together. Do your thing. Find your favourite Yahoo! Group. --~--~---------~--~----~------------~-------~--~----~ To post to this group, send email to materials-welding@googlegroups.com To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com For more options, visit this group's bolg at http://materials-welding.blogspot.com/ The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents. -~----------~----~----~----~------~----~------~--~---
Any advice for cast iron welding Sent from Yahoo Mail for iPhone
-
Q: What are equivalents for standard Q 235 B (and Q 235 A) for U-channels? ...
-
Definition of buttering from ASME Section IX, QW/QB-492 Definitions: Buttering: the addition of material, by welding, on one or bot...
-
Section I. PRINT READING 3-1. GENERAL a. Drawings . Drawing or sketching is a universal language used to convey all necessary information to...
|
No comments:
Post a Comment