[MW:1601] Re: Pneumatic test of Reinforcement Pad for Branch connection in Piping

Hi Jivan

Check at this link

 

http://www.eng-tips.com/viewthread.cfm?qid=226096&page=6


With Warmest Regards

Ganesan



 

 








 



 



Date: Wed, 18 Feb 2009 22:07:25 +0530
From: jivanadhamane@yahoo.co.in
Subject: [MW:1598] Pneumatic test of Reinforcement Pad for Branch connection in Piping
To: materials-welding@googlegroups.com

Dear Friends
 
I would like to know whether Pneumatic Test of Reinforcement Pad for branch connection of Process Piping is mandatory as per ASME B31.3. I searhed but I could not found any paragraph in ASME B31.3.
 
Regards
 
Jivan Dhamane


Cricket on your mind? Visit the ultimate cricket website. Enter now!</a
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...