[MW:1599] Re: Pneumatic test of Reinforcement Pad for Branch connection in Piping

Irrespective of, whether it is mentioned in code or not RF pad has to be pneumatically tested otherwise how will you check leakage in "welds" associated with RF pad.
Regards
Aarpee

On Wed, Feb 18, 2009 at 10:07 PM, Jivan Dhamane <jivanadhamane@yahoo.co.in> wrote:
Dear Friends
 
I would like to know whether Pneumatic Test of Reinforcement Pad for branch connection of Process Piping is mandatory as per ASME B31.3. I searhed but I could not found any paragraph in ASME B31.3.
 
Regards
 
Jivan Dhamane


Cricket on your mind? Visit the ultimate cricket website. Enter now!


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone