Re: [MW:13992] REQUIRMENT FOR TEMPORARY BLIND FLANGE USED FOR HYDROTEST

Dear Azad
 
It is unsafe to do like that
 
Can you please tell me is that on the top of flange is vent for the pressure gauge and welded to the top plate. If yes and the the plates are only welded on the edge as I understand  from the figure the  pressure is on the thinnest plate will be the same as on the thickest  which is totally unsafe.  I am totally agrees with M.Vijayan the welding of both plates should  be layered as per ULW-17(g) and fig ULW 17.4 of ASME Sec VIII, Div.1. but in that case also u canot put the vent on the top.


With Kind Regards,

Chandrakant Yadav 
LINDE PROCESS PLANT (SOUTH AFRICA)

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.