Re: [MW:13927] Welder qualification

If both the companies are under the same umbrella of quality management system, there won't be any problem



On 16-Mar-2012, at 3:37 AM, Manivannan Hemu <hemumanivannan@gmail.com> wrote:


Dear Experts,
Please clarify.

Situation: Company 'A' has given a subcontract to company 'B' for repair welding of cast components.
Company 'A'-holds qualified WPS as per ASME sec IX and issues copy of them to company 'B' to follow for his work.

Question: Can the vendor (company 'B') is permitted to make production weld by following WPS of company 'A' with  company 'B's qualified welder?  indicate code reference.

MANIVANNAN.P

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone