Dear Experts
Kindly clarify below doubt's
Standard: ASME Sec IX

I have conducted procedure qualifications(welding done with recording all parameters) on 10/10/2019 and mechanical testing where conducted on 24/11/2019 in that all the testing were cleared. So my doubt is what date need to be endorsed that is during PQR generated test date or after mechanical test conducted date.

Kindly confirm


Regards.satti

--
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/0ae78523-7f75-457f-8941-d8289a5e4d84%40googlegroups.com.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone