Wednesday, May 20, 2020

[MW:30899] AWS D1.1 -Combination of welding process

Dear all 
Kindly advice 
I have WPS for weld process fcaw + saw as per aws d1.1 

I want to use same wps for only FCAW process as saw is not feasible for few joints.

Is this allowed as per aws d1.1 or new pqr is required for single process.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAOdsS43qnrwOjNUDrkcjGozo42GT7AMERLLxmpvPieJ6ZbH0yw%40mail.gmail.com.

No comments:

[MW:35346] Cast-iron welding

Any advice for cast iron welding Sent from Yahoo Mail for iPhone