Greetings,
Engineering practices for build up, upto 10mm or 1/3rd of the thickeness usually restored by of same WPS requirement and repair weld procedures, more than required thickness shall need special approval from owner / clients, anyhow its depend upon your scenario, please check below snapshots, it maybe useful.
Regards,
Mohamed Muneeb Mahaboob
CSWIP 3.2-89247/2
ASNT-NDT-L2-RTFI-RT-UT-MT-PT.
SAP#:70021650 APs:JAPID, QCS & QCI.
(6:8) They say, "Why has no ˹visible˺ angel come with him?" Had We sent down an angel, the matter would have certainly been settled ˹at once˺, and they would have never been given more time ˹to repent˺.
Date: 2018-12-01 15:01Subject: [MW:28712] Weld metal build up to restore size-Raw material--- C45 steel--, What is welding produre to build up for restoring required sizes1, Filler metal,2, Preheat and interpass, post heat temp3. Before welding , raw material is to annealed or not??4. After completion of welding, Any Heat treatment like Normalizing, Quenching and Tempering.urgent pl .THANKS & BEST REGARDS,KG.PANDITHAN, BE, IWE, CSWIP 3.1,ASNT-Level II in PT,MT,RT & UT.International Welding Engineer.CONSULTANT-WELDING & QUALITYMobile no: +919940739349
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment