see UG 84(i) for vessel production impact test
for replacement of RT by UT see UW-51 (1)(b)(4)
best regards
Dr. Georgios Dilintas
Authorized Nuclear Inspector
Authorized Inspector Supervisor
I&F REGIONAL TECHNICAL MANAGER
BUREAU VERITAS PIRAEUS - GREECE
Tel: +30 210 40 63 113 /4 /5
Fax: +30 210 40 63 118
Cell: +30 69 44 64 62 04
Kashif Syed ---05/05/2015 14:00:52---Dear All, Good day
From: Kashif Syed <syedkashif.mech@gmail.com>
To: materials-welding@googlegroups.com
Date: 05/05/2015 14:00
Subject: [MW:23205] Production weld coupon reference and NDT requirement.
Sent by: materials-welding@googlegroups.com
Dear All,
Good day
We are doing welding on a spherical vessel. The client is asking for the production weld sample for the first 3m of welding for all the joints along with the RT.
My questions are:
1. Where is the detail reference for requirement of production test coupon in ASME Sec IX?
2. Can we replace RT with PAUT ? Is there any specific technical requirement that only RT needs to be done not PAUT on PTC. as in actual job we will be doing PAUT not RT.
Waiting for your genuine reply.
--
Thanks & Regards,
Syed Kashif Farhan
--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAJeKOw1gOqDWhv9TRG3H1sG4P9vALR-KDCmRSwnasOY7PCYoJQ%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.
This message contains confidential information. To know more, please click on the following link: http://disclaimer.bureauveritas.com
No comments:
Post a Comment