Dear Experts ,

When i review the ISO 15609 Part-1 for WPS preparation , it does not mention about Procedure Qualification method and testing.
It says only the format to be used for WPS and the necessary datas to be filled in.
So, my query is whether we need to fill the format and send to client for approval, before we start welding.
Is there any other part in ISO 15609 mention about Procedure Qualification and mechanical testing.
The material for the project is JIS SS 304L and the product is venturi tube, only GTAW process we plan to use.
Await for your reply.
Regards
Saravanan
Korea

--
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To post to this group, send email to materials-welding@googlegroups.com.
Visit this group at http://groups.google.com/group/materials-welding.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CALV1rkLv56dqQcvvz3ydgxNfeo9Hc%2B%3DRYx%3D1CmtuBfR7PvcQkQ%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35289] Welding consumable for S355J2WP material

S355 J2 WP  is a weathering structural steel  It has better atmospheric corrosion resistance. Use E 8018 - W1/W2  Electrodes This is regular...