Dear Meera,
For point no. 2: In my experience, If root pass having more concave in shape (in STT root this may happen), there might be a chance of getting cold lap in between root and hot passes. Please ensure that the shape of root pass should be flat/ little concave shape, so that proper fusion will take place during hot pass welding. Also instruct the FCAW welder to reduce the welding speed or wire feed speed in order to have proper fusion in all other passes also.
Regards,
L. Prabhu kumar,
From:
Sent: Sunday, April 04, 2010 3:37 AM
To:
Subject: [MW:4680] Difference between pipes and tubes
Hai all,
1.Please somebody can explain difference between pipes and tubes with some references.
2. In our project continuously getting repair ( Cold lap) in hot and fill pass. can u suggest some good way to avoid or rectify this.
material Used - CS dia 68,64 and 60"
Process : Root - STT, Other - FCAW shielding by gas ( Ar80%, CO2 20%- 48 CFH)
Filler metal for FCAW : A5.20 E71T-9M
Expecting reply as soon as possible.
Regards,
Meera
--
To post to this group, send email to
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
|
------------------------------------------------------------------------------------------------------------------------------------------------------------------- DISCLAIMER: The information contained in this communication is intended solely for the use of the individual or entity to whom it is addressed and others authorized to receive it. It may contain confidential or legally privileged information. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution or taking any action in reliance on the contents of this information is strictly prohibited and may be unlawful. If you have received this communication in error, please notify us immediately by responding to this email and then delete it from your system. Saipem India Projects Limited (SIPL) is neither liable for the proper and complete transmission of the information contained in this communication nor for any delay in its receipt. ------------------------------------------------------------------------------------------------------------------------------------------------------------------- |
No comments:
Post a Comment