Low pressure end may not be suitable for High pressure which will lead to safety concern during testing.

Regards,
Kingsly Geo.

On Mon, 17 Feb 2020 at 17:31, harenath jha <harenathjha@gmail.com> wrote:
High pressure and temperature

On Wed, Feb 12, 2020, 12:44 Muhammed Ibrahim PK <ibratech@gmail.com> wrote:
Gents, 

Please privide an answer fore below condition. If a valve to be installed between a line where both ends are having different pressure temperature rating. What will govern?  Higher PT rating or low PT rating? 

Reg, 
Ibrahim

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CALOPgmPJDfR8wPYYEzWFokEk6ReyNccMA8%2Bviu8TSWmMz8sFpg%40mail.gmail.com.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAPRS9UMrGPutv1aWNhp7GHruDXB__qXu54Bo1LvVx7GHiPqEXw%40mail.gmail.com.

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/materials-welding/CAAR7VZ8sYFDRmUUVMnhgozhpUJ5r8oXNU73bJ5p60DZkpob5%3Dg%40mail.gmail.com.

No comments:

Re: [MW:35507] WPS for Furnace PWHT

As per ASME B31.3, Clause 331.1.6 (b): Any required PWHT shall be carried out in accordance with the qualified WPS. For furnace PWHT inv...