Re: [MW:16549] PWHT soaking Time on SS Overlay

In my opinion it is applicable only when total PWHT time exceeds 20 hours.

On Sat, Jan 19, 2013 at 2:04 PM, venu moturu <moturuvenu@yahoo.com> wrote:
 Dear experts ,
 
The production weld ( corrosion resistance overlay (SS)  3mm was deposited on the AISI 4130 Thk 50mm  by SMAW )  PWHT soaking time was exceeded the PQR soaking time more than 25% ,recommended by ASME Sec IX .
 
QW-407.9 A separate procedure qualification is
required for each of the following:
(a) For weld corrosion-resistant overlay of A-No. 8 on
all base materials, a change in postweld heat treatment
condition in QW-407.1, or when the total time at postweld
heat treatment encountered in fabrication exceeds 20 hr,
an increase of 25% or more in total time at postweld heat
treating temperature.
 
Pl. advice on the above code case as the chemical composition on PQR meets A .no.8 of sec IX
 
 
Best  Regards
Venu Moturu
 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

[MW:34920] Tubesheet Hole step

Hello Team, I have one question any tolerance given for tubesheet Hole step. Please do needful. Regards, AP  -- https://materials-...