Hi,
Refer ASME Section 1-PW54. Please find herewith the aattached files of PW54.
Thanks & Regards,
(Karthik)
Karthikeyan.S
QA/QC Manager
German-Thai Boiler Engineering Cooperation Limited.
Rayong Factory ;
379 Moo.6 Soi 8, Tambol Pananikom,
Nikompattana, Rayong 21180 THAILAND
Tel : +66 38 897 035-9 Ext. 137
Fax : +66 38 897 034
Hand Phone: 0066 892512282
From: Sathish V P <sathishvp86@gmail.com>
To: materials-welding@googlegroups.com
Sent: Tuesday, January 22, 2013 12:23 AM
Subject: [MW:16566] Attachment welding to be carried after ASME Stamping - in Power Boilers
To: materials-welding@googlegroups.com
Sent: Tuesday, January 22, 2013 12:23 AM
Subject: [MW:16566] Attachment welding to be carried after ASME Stamping - in Power Boilers
Dear Experts,
-- We have a situation here in our boiler, Hydro test has been carried out and boiler is Stamped with ASME S Stamp.
Now few attachment welding with the pressure parts is to be carried out according to the new modification drawing.
Is there any code reference available according to ASME SEC I, if so pls guide me through the clause and section.
Thanks & regards,
Sathish.v.p
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
No comments:
Post a Comment