Monday, January 21, 2013

[MW:16566] Attachment welding to be carried after ASME Stamping - in Power Boilers

Dear Experts,

We have a situation here in our boiler, Hydro test has been carried out and boiler is Stamped with ASME S Stamp.

Now few attachment welding with the pressure parts is to be carried out according to the new modification drawing. 

Is there any code reference available according to ASME SEC I, if so pls guide me through the clause and section.

Thanks & regards,

Sathish.v.p

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 

No comments:

[MW:34919] Welder qualification certificate

Dear All     anyone can share a format for welder certificate and card format        Thanks & Best Regards Saleem manhappulath Mob:+9665...