[MW:4358] ASME B31.3 IMPACT TEST

It depends on MDMT, please provide design conditions.

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of mauricio padilla
Sent: Sunday, February 21, 2010 11:28 PM
To: materials-welding@googlegroups.com
Subject: [MW:4357] ASME B31.3 IMPACT TEST
 
 
Dear Sirs
 
Please I need information about ASME B31.3.
 
 
In piping normally are used the following materials:
1) pipes A106 Gr B /API 5L Gr B
2) fittings ( tee elbow, reducers) A234 WPB
 
My questions are:
 
1) I want to know about is it necessary a Impact testing if the wall thickness of:
 
  pipe API 5L X60 with 10 NPS and wall thickness of

12.7mm(0.5 pulg)?

38.1mm (1.5 pulg)?

2) If I have fittings  A234 WPB of NPS 10" with wall thickness of

         12.7mm(0.5 pulg)?

38.1mm (1.5 pulg)?

Please answer me.
 
Best regards
 
Mauricio