We have to build two 10" pipelines according Api 1104- one bitumen in
concrete trench and other by gas oil (buried)... we have 10% RT
.....but a part of lines are inside plant (around 30 meters -15
welds.....)
how we will inspect RT the welds inside plant ...according API or B31.3?
Also along the bitumen piping system and pipeline we have 1" hot oil
traced line .....
What kind of inspection is recommended? RT%? PT%? Visual?
Thanks
Daniel
--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding-unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
-~----------~----~----~----~------~----~------~--~---