Dear All,
Pl clarify, when the Tube to Tubesheet Mock up Test is required. Is it required when specific material combinations are there? or  for all Tube to Tubesheet welds? Give code reference pl.

Regards,
Venkatramulu

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

Re: [MW:35501] TEST COUPON ASME SEC IX

Yes, You can machine the Plate.  Prepare the Welding Running Sheet and mention 14 mm Plate machined to 8 mm Plate.  then the groove weld qua...