[MW:26701] Permanent attachments welded on shell after hydro test by contractor

Dear All,

We are constructing 2 tanks at the site, after the hydro test the subcontractor team cut one nozzle on above HHL and the supports of the same nozzles are welded with pad plate on the shell at the below level of the hydro test. what is your opinion?? they did not inform us and the Owner.


Thanks

Pinto 

--
https://materials-welding.blogspot.com/
https://www.linkedin.com/groups/122787
---
You received this message because you are subscribed to the Google Groups "Materials & Welding" group.
To unsubscribe from this group and stop receiving emails from it, send an email to materials-welding+unsubscribe@googlegroups.com.
Visit this group at https://groups.google.com/group/materials-welding.
For more options, visit https://groups.google.com/d/optout.

No comments:

[MW:35748] Re: PQR- Chemical testing requirements

As answered by everyone, chemical is not required. Notwithstanding, please note that A-No. which denotes weld metal chemical composition is ...