[MW:25787] Procedure Qualification

Hello Expert,

 

 

I have to develop  Procedure Qualification for  AISE 4130 to P1 material, no PWHT and also to meet NACE requirements.

 

I feel that buttering process GTAW/SMAW using ER 70 S2 and E7018.  Initially Buttering with 7018 both the bevel and joint fit-up and continue buttering process.

 

Do you have any comment?

 

Bala Nechur,

 

No comments:

Re: [MW:35507] WPS for Furnace PWHT

As per ASME B31.3, Clause 331.1.6 (b): Any required PWHT shall be carried out in accordance with the qualified WPS. For furnace PWHT inv...