You just delete position 1 g from wps and write All,
As per ASME Section IX if WPS is qualified in any one position of 1G
to 6G it is qualify for all the position.
Then u can attached nos of PQR with dirrent position following the
same WPS.
Regards
Israr Ahmed
Tata Projects Ltd.India
+919930308261
On Nov 11, 2:35 pm, Zulfan <zul...@insing.com> wrote:
> Dear all,
>
> please advice in our PQR mentioning position 3G and our WPS stated 1G
> is the WPS able to apply or need to run again PQR again?
> code ASME sec IX
>
> Thank
> zul
--