Tuesday, November 30, 2010

RE: [MW:8441] HOTTAP on SOUR LINE (PWHT Required)

Dear Limesh & All;

 

Thanx for your replies & advices.

 

The materials is A 106 Gr B, pipe Dia is 4” Sch 40, & we are using split tee 15 mm thick.

 

The same I had in my previous works, the issue were to qualified the welders for Temper Bead Procedure (Half bead). As per QW-290.

 

The surprise here for the client & client TPI, that, client TPI is asking to make a heating up to 300C for 30 to 60 min after completing the welding (which I search everywhere, I didn’t find such procedure in any relevant standards.)

The second surprising thing is my client, is asking to make preheating to 350C for 3 hours before starting the work plus hydrogen baking.

 

My point is, the life line is wet LPG, H2S present 2500 PPM, which is very high, plus if I keep heating the line up to this temperature, I need to ensure it will not imply any unwarranted impacts , thus jeopardizing the operational LPG unit itself.

 

 

Regards

Majdi Elyyan

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of limesh M
Sent: Monday, November 29, 2010 7:56 AM
To: materials-welding@googlegroups.com
Subject: Re: [MW:8424] HOTTAP on SOUR LINE (PWHT Required)

 

Dear Majdi,

 

You didn't mention the material designation(pipe and split tee material) and thickness of the pipe/split tee material.If you could provide it,it will be easy for experts to analyse your query.I also have interest in this matter.

 

 

Regards,

 

Limesh

On Sun, Nov 28, 2010 at 6:45 PM, Majdi N Elyyan <melyyan@gmail.com> wrote:

Dear All;

 

We have a hot tap on LPG line (Sour service) which require PWHT.

The run Pipe is 4”, the branch is also 4”, split tee will be used.

As per shell DEP-31.38.60.10 – for Hot tapping, clearly mention:

Hot-tap welding should not normally be performed on materials which require post-weld

heat treatment. However, if stress relieving or post-weld heat treatment is required, a

specialist shall be consulted to assess whether it is feasible to make the specific

hot-tapping operation with post-weld heat treatment.

Note: Stress-relieving may be required if a material is susceptible to stress corrosion cracking and post-weld

heat treatment may be specified by the design code if the wall thickness is greater than a certain limit.

 

& since we have no other options, we have to do the hot tap on the same, kindly advice WPS & PWHT procedures

 

Thank all in advance..

 

Regards

Majdi Elyyan

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...