Friday, November 26, 2010

[MW:8394] Re: HOT PASS

** More current is required to melt the already solidified root + the
slag deposits if any lying on the root pass needs more current to melt
on

** not neccesarily ,welding process in hot pass need not be same


yogesh

On Nov 24, 9:46 pm, srinivas rao <ksrv...@gmail.com> wrote:
> Hi Gents,
>
> I have  doubt reg HOT PASS.
>
> 1. what is the purpose of doing HOT PASS with more speed and high current?
>
> 2. Should the Welding Process used for Root be the same for HOT PASS? If not
> necessarily then how should we decide?
>
> Thank you All
>
> Regards,
>
> Vasu

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

Re: [MW:34913] Filler wire

E71T-1C  is Charpy Impact tested at -20degC E71T-1CJ is Charpy impact tested at -40degC. AWS Classification for FCAW is only a supplementary...