Saturday, November 27, 2010

[MW:8403] RE: 8391] production test coupon requirement as per ASME SEC VIII DIV 1

Dear Asad,

Please see the flow chart prepared by me according to ASME Sec-VIII Div. 1 for PTC.

Please correct me if anything is wrong.

 

Best regards,

 

Shadab Alam Ansari

Welding Engineer

 

cid:image001.gif@01CB80C0.5B165EE0

For Gulf Heavy Industries Co

One of  Al-Bassam Group of Companies

 

Cell Phone No: 00966502090165, Fax No:0096633410105
Telephone No: 0096633400098 (5 Lines) Ext: 232

Email: ansari@ghi.com.sa

Web: "www.ghi.com.sa"

 

Save paper, don't print any emails unnecessarily. Let's save environment for future generation....

 

From: materials-welding@googlegroups.com [mailto:materials-welding@googlegroups.com] On Behalf Of asad azmi
Sent: Friday, November 26, 2010 2:00 PM
To: materials-welding@googlegroups.com
Subject: [MW:8391] production test coupon requiorement as per ASME SEC VIII DIV 1

 

Dear all,

 

Greetings.

 

Please inform me PTC(Production test coupon requirement) for below details--

 

Construction Code :  ASME SEC VIII DIV 1

 

Shell Material :   SA 387 GR 12 CL 2,  65 & 70 Thk.

 

MDMT :  0 Deg Celcius

 

Impact test is required as per  ASME SEC VIII DIV 1.

 

The Heat number for shell material for 3 vessels is not same.

 

 

3 vessels are required to be fabricated as per the above requirement for single  client. The vessels are going to to be erected at one location only. 

 

The thichkness of shell material for 1 vessel is 65 Thk and for other 2 vessels is 70 Thk. Diameter and Length of the vessel is different. Only MDMT and material is same.

 

Please inform me whether seprate  PTC( production test coupon)  is required for each  vessel  OR 1 PTC attached with longseam/Circ. Seam of only 1 vessel  will also represent other 2 vessels also.

 

Whether 2 PTC ( 1 for longseam &  1 for circumferential seam for 1 vessel)  is enough for all three vessels OR total of 6 PTC are required for 3 vessels.

 

Please give code reference.

 

Thanks in advance for your valuable suggestions.

 

Regards

 

Asad Azmi

 

 

 

 

--
To post to this group, send email to materials-welding@googlegroups.com
To unsubscribe from this group, send email to materials-welding+unsubscribe@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.

No comments:

[MW:34866] Presentation for WPS ,PQR AND WPQ as per ASME Sec IX in power point

Dear Experts.        If anyone having presentation of WPS,PQR and WPQ  as per ASME  SEC.IX  in power point then please share . Regards Sanja...